LOCATION:


Key elements of the contract
- Translocation of orchids to an area approximately 500m away.
- Excavated and installed a lightweight concrete infill to reduce the potential risk of delay due to poor ground conditions and obstructions from affecting the pipework installation works.
- Tunnel boring of approximately 165m new 1200mm diameter jacked concrete pipework at 8m depth to invert.
- Installation of three, three metre diameter 8m deep manholes to adoptable standard.
- Installation of a new pedestrian footpath to the perimeter of the new development.
A Tunnel Boring Machine (TBM), also known as a “mole” or “worm”, is a specialised machine used to excavate tunnels through various types of soil and rock, often used in large infrastructure projects.
These works will create a corridor for all future utilities diversions while also undertaking a comprehensive UXO survey to inform the wider development and enable progression through the final design stage.
Outcome
TBM commenced the first of two drives in November and completed with extraction just prior to the Christmas period. The second drive was then commenced January 2025 and completed mid-March. DCWW conducted their CCTV and visual inspections one week after completion and signed off with no recommendations for snagging.




