Manor Farm Culverts

LOCATION:

Staines, Surrey
A £3.5m contract to install two box section culverts forming a tunnel. A conveyor belt is then to be installed to transport aggregate from the fields of Manor Farm to Brett Aggregate’s quarry.

Six precast concrete units were installed below a public footpath and eight below Ashford Road. Each weighs 20T. These units join to form a tunnel to house the conveyor.

Phase one:

  • Open cut excavations.
  • Installation of five precast concrete sections using 50t excavator and culvert puller.
  • Installation of wing walls and head walls.
  • Backfill and installation of handrails.

Phase two:

  • Traffic management taking Ashford Road to a single lane.
  • Installation of piling and crane mats.
  • Installation of dewatering system, sheet piled cofferdam and frame.
  • Support underground services and excavation.
  • Installation of precast concrete sections using 300t crane and culvert pullers.
  • Cast in situ base, wing walls and head walls.
  • Backfill, remove piles, install temporary road.
  • Whole process repeated to other side of Ashford Road.

Challenge

Overcoming high groundwater conditions and multiple buried services.

Solution

We introduced a dewatering system to enable works to continue through periods of exceptionally wet weather.

We assisted our customer to produce a temporary works design to ensure buried services were appropriately protected throughout and carried out additional enabling works.

Outcome

The project was successfully completed in August 2024.

Winner of a divisional Right Works Award in 2023.

Similar projects